☰ Docs

Post-Build Floor Prep & Paint

10x12 Gable Shed — 222 Gibson St SE · Phase 5, before move-in · Getting the PT deck ply from as-built to painted.

Order of operations

  1. Confirm dry — sprinkle test
  2. Test paint adhesion on an offcut
  3. Set proud nail heads flush
  4. Fill nail holes, tearout and voids — exterior wood filler
  5. Ramp the 1/8" seam step — feather on the low side only
  6. Sand 80–100 grit, then vacuum thoroughly
  7. Seal the seams — flexible sealant, full cure per label
  8. Two coats porch & floor enamel

Sealant goes on before paint, not after — you want the enamel over it, sealing its edges. Sanding comes before sealing so you're not cutting into cured sealant.

1 · Is it dry?

Sprinkle test. Flick water onto the surface in a few places.

What happensVerdict
Drops bead up and sitToo wet. Wait
Drops soak in within ~30 secondsDry enough

Installed August 2026 and painted before move-in, the floor gets months of drying — this should pass comfortably. Test anyway. Enamel over wet PT blisters and peels no matter how good the prep was.

2 · Nail heads — flush, never sunk

A head driven through the face veneer loses most of its shear value, and this floor is structural. The target is flush, not countersunk.

ToolUse
Smooth-faced hammerThe answer. One or two light taps brings a proud head flush without marking
Milled (waffle) face framing hammerThe cause. That grid stamps into the ply — this is almost certainly what's marring the surface
Nail set, 1/8" tipStrike the tool, not the wood. But it's built to drive heads below the surface — use it only for a final light tap

If you're chasing many proud heads, the gun's depth-of-drive is shallow or pressure is sagging. Set it on a scrap and re-check when the compressor cycles or the temperature changes. Light hammer marks sand out in step 6; a crater through the veneer does not.

3 · The 1/8" seam step — as-built

Condition: at one seam, one sheet sits a solid 1/8" below its neighbor. Cause not diagnosed before nail-off — most likely a joist installed with less crown, since 1/8" is well outside the ±1/32" mill tolerance for 23/32 ply. Sheets are fully nailed at 6"/12", so pulling and shimming was rejected: extracting ring shanks from PT ply does more damage than the step.

The ramp — feather the low side only

  1. Exterior wood filler, or a patching compound rated for wood subfloors
  2. Thin lifts. Two or three passes — 1/8" in one application cracks
  3. Feather 8 to 12 inches back from the seam. That's a slope near 1:100, imperceptible underfoot and invisible under paint
  4. Sand with a long block or orbital so you cut the ramp flat rather than following its contour
  5. Prime and paint

4 · Filling the seams

The seams were cut roughly 1/16" scant, and the deck carries about 0.16" of racking that migrated into the cut pieces at the south and east. The gaps are real and worth closing.

ProductMovementPaintableFloor trafficVerdict
Self-levelling polyurethane (Sikaflex SL, NP1 SL)±25–35%YesRated for itBest. Flows flat on its own — no tooling, no ridge under the enamel
MS polymer / hybrid (OSI Quad Max, Loctite PL)±25–50%YesYesNearly as capable, far easier to tool and clean up
Siliconized acrylic latex caulk±7.5%YesNoToo soft — scuffs, collects dirt
SiliconeHighNoDisqualified: won't take paint

Three things decide whether it lasts

Honest expectation: most joints hold indefinitely; one or two may show a hairline separation after a few seasons. Touch-up is a five-minute job.

5 · Sanding — this matters more than filling

PT plywood is rough, and the grain raises as it dries. A pass with 80 to 100 grit does more for the finished look than any seam treatment, and it materially improves paint adhesion.

Then vacuum thoroughly. Enamel over sanding dust is a bad finish, and PT dust is worth not breathing or leaving behind — wear a mask and clean up properly.

6 · Paint

ItemSpec
ProductPorch & floor enamel, 1 gal + roller kit
CoatsTwo
WhenEnd of Phase 5, before move-in
Cost / order~$90 · Order 3 (line o3-16)
Coverage needed120 sq ft × 2 coats

Prime first if the adhesion test suggests it — the scrap test in step 1 tells you. Let the sealant cure fully before the first coat; polyurethane in particular needs its full stated time, not just skin-over.

Provenance

Written Aug 19, 2026 from the floor-prep discussions during deck installation. As-built conditions recorded here — the 1/8" seam step, the ~0.16" of deck racking, the scant-cut seams — are specific to this build and were logged as they happened. Related: Base & Deck Construction for the deck itself, Build Guide Phase 5, Orders & Deliveries for the enamel line.