Roadmap

Everything left on the shed, in order · updated Oct 5, 2026 · full detail in the Build Guide · source: Roadmap.md

0%

Where we are

Walls sheathed; rafters, ridge and bracing up; the deck plywood and panel clips are on site. The deck is planned for Tuesday, Oct 6.

Next up

  • Shim the gapped ridge joints
  • Toe-screw the 10 interior rafters
  • Collar ties (guide)

Close the roof Build Guide Phase 4

Get the roof weathertight, then trimmed and shingled.

  1. Before the deck

    Shim any ridge joint with daylight at the plumb cut, toe-screw each of the 10 interior rafters into the ridge, then install the five collar ties. All three are easier while the roof is open.

    Watch for: Shim before toe-screwing, and tap shims in snug, not hard.
  2. Deck

    19/32 sanded plywood, B face down (it's your ceiling). Lower course first with its end seam on the center rafter, panel clips at the course seam, 3″ ring nails at 4″ on sheet ends and gable rafters and 6″ elsewhere, rafters only.

    Watch for: The deck edge now sits a finger (~3/4″) past the future shadow-board face, so measure a fascia and a shadow board first and size the overhang from them. Measure the upper course on site; keep 1/8″ gaps.
  3. ProArmor

    Cap-stapled in the pattern printed on the roll, 3″ course laps, 6″ over the ridge from each side. Wrap the rakes; leave the bottom 6–8″ loose at the eaves for the drip edge.

    Watch for: Rated for 90 days of exposure, so the trim and shingles don't have to follow right away.
  4. Dry-in

    The building is weathertight on top. Safe to pause. The ridge diagonals and ridge props can come out once the deck is nailed off.

  5. Eave trim

    Staple 12–14″ ProArmor strips (the bands) along the top of the east and west walls, bottom 3–4″ left loose for the wall felt later. Then the eave fascia and shadow board, tops flush with each other.

    Watch for: Each eave board needs about 144-3/4″. Measure your 12′ boards before cutting.
  6. Gable ends

    Three plywood pieces per gable (a middle piece under the peak plus two corners), scribed to the end rafters. Then the band, then the rake fascia and shadow board, running out over the ends of the eave trim to finish flush.

    Watch for: The vent goes in the solid middle piece later, so no seam crosses it.
  7. Drip edge

    At the eaves it slides under the loose ProArmor strip, which then staples back down over its flange. At the rakes it goes over the ProArmor. Square-cut deck edges; don't bend it.

  8. Shingles

    Scrap-test the 3/4″ nails on a deck offcut first. Cut-your-own starter, six nails per shingle, Loctite dabs under the rake ends, cut 3-tab ridge caps.

    Watch for: Nails flush, never sunk.
  9. Roof done

    The temporary wall braces can come out any time; take the cross-wall spreader out after the shingles.

Walls and openings Build Guide Phase 5

Openings first, then felt, trim and cedar shingles, so every layer laps the right way.

  1. Finalize the window and door details

    On paper: the window sill pan and sill board, the stops that hold the sash, casing widths and head drip cap; the door threshold and its flashing; the gable vent model.

    Watch for: These set the cut lines and the flashing order, so they come before the felt.
  2. Cut the window openings

    Cut the two openings out of the west-wall sheathing, clean to the framing. Cover them with plastic or a plywood scrap until the sash go in.

  3. Flash the openings

    Sill pans and flashing tape on the side walls of each window opening. At the door, the threshold membrane: over the floor edge and down the rim, turned up a few inches onto each door post.

  4. Wall felt

    About 2 rolls of #30 felt from a roofing supply house, cap-stapled, bottom up with 2″ laps. Around each opening, every layer laps the one below it. The top courses slide up under the loose ProArmor bands. Set the gable vents in the same pass, centered with their trim about 2″ below the rake fascia.

    Watch for: Never lap felt over a band; it goes under.
  5. Trim

    Corner boards, window trim (sill, casings, drip cap over the head casing) and the door casing run all the way down to the bottom of the wall, over flashing tape.

    Watch for: Trim goes up before the shingles because the shingles butt into it.
  6. Cedar wall shingles

    With the Freeman nailer and stainless ring-shank coil nails. Pick the nail length (1-1/4″ or 1-1/2″) and buy the coils first.

  7. Weathertight shell

    Roof and walls are closed and finished outside. Everything left can happen at your own pace.

Doors, ramp and finish Build Guide Phase 5

The parts you'll see and use every day.

  1. Sash

    Rehab them any time; install with the stops after the wall shingles, so the old glass stays clear of all the hammering.

  2. Doors

    Build, set the glass panels, hang. A threshold board goes over the membrane, overhanging the rim with a drip groove.

  3. Ramp

    Cut the plywood strip out below the door, screw the ramp stringers to the pressure-treated rim joist, and tuck the top board under the threshold's overhang.

  4. Paint

    The accent color on the doors, sash and stops, chosen against the Weathered Gray roof.

  5. Floor

    Prep and paint once the floor plywood is dry. Fill the brace screw holes as part of the prep.

  6. Interior liner and pegboard

    Any time after dry-in.

  7. Finish up

    Remove the last temporary bracing, clear the gravel gap along the fence side, and build the fieldstone skirt.

  8. Done

    The shed is finished.

Decisions still open

Grouped by when you need them.

Soon — for the roof

  • Eave fascia: flush with the shadow board, or raised ~7/8″ (before the eave trim)
  • Optional center-post rim supports (only worth it before shingling)

Before the wall felt

  • Window sill pan, sill board, stops, casing and drip cap
  • Door threshold detail
  • Gable vent model (candidate: Al's Millworks 18″ octagon cedar vent, 20″ overall with brickmould)

Later

  • Wall-shingle nail length (1-1/4″ or 1-1/2″), before buying the coils
  • Cedar starter overhang (1″ vs 1/4″ in different docs)
  • Finish on the rafters and ceiling (needs re-visiting)
  • Paint accent color

Tap a step's number to mark it done. Checkmarks are saved in this browser only.